Road marking and staking out across the Mongu Housing Development, set out on site from the approved plans, specifications and drawings.
The contract was signed on 27 April 2026 and the works were completed on 14 May 2026.
Our Client’s Challenge
Roads and plots had to be marked on the ground exactly as designed, so construction could proceed against the approved plans without rework.
Our Approach And Solution
Control was established and checked before setting out. Road centrelines, edges and plot positions were staked from design coordinates and checked against the drawings as the work progressed.
Outcome
The client issued a certificate of completion on 17 August 2026 confirming the works comply with the purchase order, plans, specifications and drawings. The certificate and a reference are available on request.